NEW QUESTION 1
Which Perform Quality Control tool graphically represents how various elements of a system interrelate?

  • A. Control chart
  • B. Flowchart
  • C. Run chart
  • D. Pareto chart

Answer: B

NEW QUESTION 2
Perform Integrated Change Control is the process of:

  • A. Reviewing, approving, and managing all change requests
  • B. Facilitating change management, manuals, or automation tools
  • C. Comparing actual results with planned results in order to expand or change a project
  • D. Documenting changes according to the change control system by the change control board

Answer: A

NEW QUESTION 3
Which input to the Plan Risk Management process provides information on high-level risks?

  • A. Project charter
  • B. Enterprise environmental factors
  • C. Stakeholder register
  • D. Organizational process assets

Answer: A

NEW QUESTION 4
The process of identifying the stakeholders' information needs is completed during:

  • A. Plan Communications.
  • B. Manage Stakeholder Expectations.
  • C. Stakeholder Analysis.
  • D. Identify Stakeholder

Answer: A

NEW QUESTION 5
Outputs of the Control Communications process include:

  • A. expert judgment and change requests.
  • B. work performance information and change requests.
  • C. organizational process asset updates and an issue log.
  • D. project management plan updates and an issue lo

Answer: B

NEW QUESTION 6
Which type of managers do composite organizations involve?

  • A. Functional managers and manager of project managers
  • B. Functional managers only
  • C. Project managers only
  • D. Technical managers and project managers

Answer: A

NEW QUESTION 7
The following is a network diagram for a project.
CAPM dumps exhibit
How many possible paths are identified for this project?

  • A. 3
  • B. 4
  • C. 6
  • D. 7

Answer: B

NEW QUESTION 8
The Project Human Resource Management process that involves confirming human resource availability and obtaining the team necessary to complete project activities is:

  • A. Acquire Project Team.
  • B. Plan Human Resource Management.
  • C. Manage Project Team.
  • D. Develop Project Tea

Answer: A

NEW QUESTION 9
Which type of graphic is displayed below?
CAPM dumps exhibit

  • A. Work breakdown structure
  • B. Context diagram
  • C. Control chart
  • D. Pareto diagram

Answer: A

NEW QUESTION 10
Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?

  • A. WBS directory
  • B. Activity list
  • C. WBS
  • D. Project schedule

Answer: C

NEW QUESTION 11
A graphic display of project team members and their reporting relationships is known as a:

  • A. Resource calendar.
  • B. Project organization chart.
  • C. Resource breakdown structure (RBS).
  • D. Responsibility assignment matrix (RAM).

Answer: B

NEW QUESTION 12
Which type of estimating can produce higher levels of accuracy, depending upon the sophistication and underlying data built into the model?

  • A. Bottom-up
  • B. Three-point
  • C. Parametric
  • D. Analogous

Answer: C

NEW QUESTION 13
Whose approval may be required for change requests after change control board (CCB) approval?

  • A. Functional managers
  • B. Business partners
  • C. Customers or sponsors
  • D. Subject matter experts

Answer: C

NEW QUESTION 14
Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?

  • A. Facilitation techniques
  • B. Expert judgment
  • C. Analytical techniques
  • D. Variance analysis

Answer: C

NEW QUESTION 15
How is the schedule variance calculated using the earned value technique?

  • A. EV less AC
  • B. AC less PV
  • C. EV less PV
  • D. AC less EV

Answer: C

NEW QUESTION 16
When calculating the cost of quality (COQ) for a product or service, money spent for cost of conformance would include the areas of:

  • A. training, testing, and warranty work.
  • B. equipment, rework, and scrap.
  • C. training, document processes, and inspections.
  • D. inspections, rework, and warranty wor

Answer: C

NEW QUESTION 17
How many Project Management Process Groups are there?

  • A. 3
  • B. 4
  • C. 5
  • D. 6

Answer: C

NEW QUESTION 18
A disadvantage associated with virtual teams is that they:

  • A. Require communication technology that is not readily available.
  • B. Create difficulties when including people with disabilities.
  • C. Often cannot accommodate teams that work different hours or shifts.
  • D. Create the possibility for misunderstandings to aris

Answer: D