PK0-004 | High quality PK0-004 Braindumps 2021
for CompTIA certification, Real Success Guaranteed with Updated . 100% PASS PK0-004 CompTIA Project+ Certification Exam exam Today!
Online CompTIA PK0-004 free dumps demo Below:
NEW QUESTION 1
Which of the following documents should be used to provide high-level reporting to key stakeholders?
- A. Dashboard
- B. Communication plan
- C. Statement of work
- D. Project charter
Answer: A
Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 325
NEW QUESTION 2
A carpenter on a project team reports there is insufficient time to accomplish tasks on schedule. Which of the following is the FIRST step the project manager should take?
- A. Assess the risk register’s new items.
- B. Review the task start and finish dates.
- C. Obtain additional resources.
- D. Analyze the assigned hours.
Answer: A
NEW QUESTION 3
Which of the following is a team-building stage that involves the team learning to trust one another’s abilities and begin working together as a productive group?
- A. Norming
- B. Forming
- C. Storming
- D. Performing
Answer: A
Explanation: Norming is where things begin to calm down. Team members know each other fairly well by now. They’re comfortable with their positions in the team, and they begin to deal with project problems instead of people problems. “Decisions are made jointly at this stage, and team members “exhibit mutual respect and familiarity with one another.
NEW QUESTION 4
A vendor has accepted a proposed project from a customer.
Which of the following is MOST likely to be the first document created by the project manager?
- A. Project charter
- B. Project management plan
- C. Project statement of work
- D. Project schedule
Answer: C
Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 299
NEW QUESTION 5
Which of the following statements are correct regarding project management? (Select two.)
- A. A project can be part of an organization’s program management.
- B. An organization’s portfolio will include programs.
- C. A program has ADefined start and finish.
- D. An organization’s portfolio is a temporary and unique endeavor.
- E. A project portfolio will be managed under program management.
Answer: BC
NEW QUESTION 6
A new high-priority project is assigned to the project manager with a fully formed budget, deadline, and scope. The project manager is creating the project schedule.
Which of the following calculations accurately shows the critical path?
- A. 20 days
- B. 39 days
- C. 49 days
- D. 52 days
Answer: D
NEW QUESTION 7
A project manager is managing a project with a hard deadline in two weeks. At the current rate of progress, the project will not finish on time.
Which of the following techniques is MOST likely to be used to complete the project on time?
- A. Throttling
- B. Crashing
- C. Resource leveling
- D. Resource smoothing
Answer: B
Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 170
NEW QUESTION 8
During the testing phase, a team member has informed the project manager that the test environment was set with inadequate client information, putting the project in jeopardy. Which of the following should the project manager do NEXT?
- A. Ask the team member to move to ADifferent test environment.
- B. Ask the team member to refrain from testing the scenarios.
- C. Revisit the risk management plan and provide corrective actions.
- D. Revisit the contingency plan and provide corrective actions.
Answer: D
NEW QUESTION 9
ABusiness has implemented a new online performance management tool that allows functional and project managers to rate employees online.
This action is known as which of the following?
- A. Business process change
- B. Organizational change
- C. Internal reorganization
- D. Business continuity planning
Answer: A
Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 297
NEW QUESTION 10
A quality auditor finds suspicious code during a software test. For which of the following could this be a trigger?
- A. Incident response
- B. Quality control
- C. Resource changes
- D. Business continuity response
Answer: A
NEW QUESTION 11
Which of the following documents need to be updated as events occur during a project? (Select TWO).
- A. Change request
- B. Risk register
- C. Meeting minutes
- D. Issue log
- E. Status report
Answer: CE
NEW QUESTION 12
A project manager is assigned to an ongoing project. Which of the following is the FIRST document the protect manager should review?
- A. Project schedule
- B. Action items
- C. Project charter
- D. Communication plan
Answer: A
NEW QUESTION 13
A project manager has an opportunity to add a highly skilled expert to the team who can increase the probability of the project’s success.
Which of the following risk strategies should the project manager adopt?
- A. Exploitation
- B. Avoidance
- C. Acceptance
- D. Mitigation
Answer: A
Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 239
NEW QUESTION 14
A project manager is justifying a required change with the associated impact on the project. Which of the following is the NEXT step?
- A. Implementation
- B. Approval
- C. Validation
- D. Auditing
Answer: B
Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 294
NEW QUESTION 15
An organization has multiple projects that are taking place simultaneously.
Which of the following should be tasked with ensuring resources are appropriately allocated to projects?
- A. PMO
- B. Project sponsor
- C. Project coordinator
- D. HR
Answer: B
Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 82
NEW QUESTION 16
A project schedule lists a resource as 50% because it likely:
- A. is a shared resource.
- B. depict a resource shortage.
- C. signifies overallocation of a resource.
- D. notes underallocation of a resource.
Answer: A
NEW QUESTION 17
A WBS is being developed for a project.
Which of the following would be BEST suited to contribute cost and time estimates for the project activities?
- A. Project team members
- B. Project sponsor
- C. Project manager
- D. Project scheduler
Answer: C
Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 82
Recommend!! Get the Full PK0-004 dumps in VCE and PDF From Certleader, Welcome to Download: https://www.certleader.com/PK0-004-dumps.html (New 246 Q&As Version)