PMP | Top Tips Of Update PMP Study Guide

Your success in PMP PMP is our sole target and we develop all our PMP braindumps in a way that facilitates the attainment of this target. Not only is our PMP study material the best you can find, it is also the most detailed and the most updated. PMP Practice Exams for PMP PMP are written to the highest standards of technical accuracy.

Online PMP PMP free dumps demo Below:

NEW QUESTION 1

Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?

  • A. Identify Risks
  • B. Plan Risk Management
  • C. Perform Qualitative Risk Analysis
  • D. Perform Quantitative Risk Analysis

Answer: C

NEW QUESTION 2

Create WBS is part of which of the following Knowledge Areas?

  • A. Project Integration Management
  • B. Project Scope Management
  • C. Project Time Management
  • D. Project Cost Management

Answer: B

NEW QUESTION 3

PMP dumps exhibit
Which of the following is the correct network diagram for the table?

  • A. Begin-A-C-D-E-End-B-D
  • B. Begin-A-B-C-D-E-End
  • C. Begin-A-B-D-E-End A-C-D
  • D. Begin-A-C-D-E-End-B-C

Answer: A

NEW QUESTION 4

Which is an enterprise environmental factor?

  • A. Marketplace conditions
  • B. Policies and procedures
  • C. Project files from previous projects
  • D. Lessons learned from previous projects

Answer: A

NEW QUESTION 5

Which is one of the major outputs of Sequence Activities?

  • A. Responsibility assignment matrix (RAM)
  • B. Work breakdown structure (WBS) update
  • C. Project schedule network diagram
  • D. Mandatory dependencies list

Answer: C

NEW QUESTION 6

In Plan Risk Management, which of the management plans determines who will be available to share information on various risks and responses at different times and locations?

  • A. Schedule
  • B. Quality
  • C. Communications
  • D. Cost

Answer: C

NEW QUESTION 7

Which tool or technique is used in validating the scope of a project?

  • A. Facilitated workshops
  • B. Interviews
  • C. Inspection
  • D. Meetings

Answer: C

NEW QUESTION 8

Types of internal failure costs include:

  • A. inspections.
  • B. equipment and training.
  • C. lost business.
  • D. reworking and scrapping.

Answer: D

NEW QUESTION 9

During project selection, which factor is most important?

  • A. Types of constraints
  • B. Internal business needs
  • C. Budget
  • D. Schedule

Answer: B

NEW QUESTION 10

For a project to be successful, the project team must do which of the following?

  • A. Complete the project in sequential phases.
  • B. Overlook minor stakeholders.
  • C. Produce ongoing repetitive products, services, or results.
  • D. Select the appropriate processes required to meet the project objective.

Answer: D

NEW QUESTION 11

Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?

  • A. Estimate Costs
  • B. Control Costs
  • C. Determine Budget
  • D. Plan Cost Management

Answer: B

NEW QUESTION 12

Who is responsible for determining which processes from the Process Groups will be employed and who will be performing them?

  • A. Project sponsor and project manager
  • B. Project sponsor and functional manager
  • C. Project manager and project team
  • D. Project team and functional manager

Answer: C

NEW QUESTION 13

While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?

  • A. Communications management plan
  • B. Human resource plan
  • C. Quality management plan
  • D. Procurement management plan

Answer: A

NEW QUESTION 14

Market conditions and published commercial information are examples of which input to the Estimate Costs process?

  • A. Scope baseline
  • B. Organizational process assets
  • C. Enterprise environmental factors
  • D. Risk register

Answer: C

NEW QUESTION 15

Project contracts generally fall into which of the following three broad categories?

  • A. Fixed-price, cost reimbursable, time and materials
  • B. Make-or-buy, margin analysis, fixed-price
  • C. Time and materials, fixed-price, margin analysis
  • D. Make-or-buy, lump-sum, cost-plus-incentive

Answer: A

NEW QUESTION 16

Which Knowledge Areas include processes from the Closing Process Group?

  • A. Project Quality Management and Project Time Management
  • B. Project Scope Management and Project Risk Management
  • C. Project Stakeholder Management and Project Cost Management
  • D. Project Integration Management and Project Procurement Management

Answer: D

NEW QUESTION 17

The progressive detailing of the project management plan is called:

  • A. expert judgment.
  • B. rolling wave planning.
  • C. work performance information.
  • D. specification.

Answer: B

NEW QUESTION 18

When are deliverables accepted or not accepted?

  • A. When the project is initiated
  • B. As an output of the scope verification process
  • C. When the project is closing
  • D. In the contract closure process

Answer: B

NEW QUESTION 19

The probability and impact matrix is primarily used to:

  • A. Quantify risk issues for trends during a quality audit.
  • B. Develop a risk register for risk planning.
  • C. Evaluate each risk’s importance and priority during Perform Qualitative Risk Analysis.
  • D. Define risk and compare impacts during Perform Quantitative Risk Analysis.

Answer: C

NEW QUESTION 20

Which piece of information is part of the WBS Dictionary?

  • A. Responsible organization
  • B. Change requests
  • C. Validated deliverables
  • D. Organizational process assets

Answer: A

NEW QUESTION 21

Outputs from constituent processes might be used as:

  • A. Inputs to other processes.
  • B. Proof of process completion.
  • C. Identification of project tasks.
  • D. Indicators to eliminate project redundancies.

Answer: A

NEW QUESTION 22
......

Thanks for reading the newest PMP exam dumps! We recommend you to try the PREMIUM Downloadfreepdf.net PMP dumps in VCE and PDF here: https://www.downloadfreepdf.net/PMP-pdf-download.html (918 Q&As Dumps)