Master the PMP Project Management Professional content and be ready for exam day success quickly with this Exambible PMP brain dumps. We guarantee it!We make it a reality and give you real PMP questions in our PMP PMP braindumps.Latest 100% VALID PMP PMP Exam Questions Dumps at below page. You can use our PMP PMP braindumps and pass your exam.

Online PMP free questions and answers of New Version:

NEW QUESTION 1

An associate who calculates fees daily to support the department is doing which of the following?

  • A. Phase work
  • B. Project work
  • C. Lifecycle work
  • D. Operations work

Answer: D

NEW QUESTION 2

Which of the following makes changes to formally control documentation to reflect modified or additional ideas or content?

  • A. Defect repair
  • B. Updates
  • C. Corrective action
  • D. Performance reports

Answer: B

NEW QUESTION 3

Sensitivity analysis is typically displayed as a/an:

  • A. Decision tree diagram.
  • B. Tornado diagram.
  • C. Pareto diagram.
  • D. Ishikawa diagram.

Answer: B

NEW QUESTION 4

What is the name of the statistical method that helps identify which factors may influence
specific variables of a product or process under development or in production?

  • A. Failure modes and effects analysis
  • B. Design of experiments
  • C. Quality checklist
  • D. Risk analysis

Answer: B

NEW QUESTION 5

A project lifecycle is defined as:

  • A. a collection of generally sequential and sometimes overlapping project phases.
  • B. a process required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
  • C. a recognized standard for the project management profession.
  • D. the application of knowledge, skills, tools, and techniques to project activities to meet the project requirements.

Answer: A

NEW QUESTION 6

Which process develops options and actions to enhance opportunities and reduce threats to project objectives?

  • A. Identify Risks
  • B. Control Risks
  • C. Plan Risk Management
  • D. Plan Risk Responses

Answer: D

NEW QUESTION 7

The Monitoring and Controlling Process Group includes processes that:

  • A. Establish the scope, objectives, and course of action of a project,
  • B. Define a new project or a new phase of an existing project.
  • C. Track, review, and regulate the progress and performance of a project.
  • D. Complete the work defined in the project management plan.

Answer: C

NEW QUESTION 8

Which of the following is an output from Control Scope?

  • A. Change requests
  • B. Variance analysis
  • C. Accepted deliverables
  • D. Requirements documentation

Answer: A

NEW QUESTION 9

Which of the following involves making information available to project stakeholders in a timely manner?

  • A. Plan Communications
  • B. Performance reporting
  • C. Project status reports
  • D. Distribute Information

Answer: D

NEW QUESTION 10

A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication?

  • A. Efficient
  • B. Effective
  • C. Push
  • D. Pull

Answer: B

NEW QUESTION 11

Plan Risk Management is the process of defining how to:

  • A. Communicate identified risks to the project stakeholders.
  • B. Conduct risk management activities for a project.
  • C. Analyze the impact a specific risk may have on the project.
  • D. Address unexpected risks that may occur during a project.

Answer: B

NEW QUESTION 12

The Project Management Process Group in which performance is observed and measured regularly from project initiation through completion is:

  • A. Executing.
  • B. Initiating,
  • C. Monitoring and Controlling.
  • D. Planning.

Answer: C

NEW QUESTION 13

Which type of managers do composite organizations involve?

  • A. Functional managers and manager of project managers
  • B. Functional managers only
  • C. Project managers only
  • D. Technical managers and project managers

Answer: A

NEW QUESTION 14

In which process is a project manager identified and given the authority to apply resources to project activities?

  • A. Acquire Project Team
  • B. Develop Project Management Plan
  • C. Manage Project Execution
  • D. Develop Project Charter

Answer: D

NEW QUESTION 15

When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?

  • A. Bottom-up
  • B. Parametric
  • C. Analogous
  • D. Three-point

Answer: A

NEW QUESTION 16

An output of the Develop Project Team process is:

  • A. Organizational process assets.
  • B. Enterprise environmental factors updates.
  • C. Project staff assignments.
  • D. Organizational charts and position descriptions.

Answer: B

NEW QUESTION 17

In the Develop Project Team process, which of the following is identified as a critical factor for a project's success?

  • A. Team meetings
  • B. Subcontracting teams
  • C. Virtual teams
  • D. Teamwork

Answer: D

NEW QUESTION 18

Which of the following processes audits the quality requirements and the results from quality control measures to ensure appropriate quality standards and operational definitions are used?

  • A. Perform Quality Control
  • B. Quality Metrics
  • C. Perform Quality Assurance
  • D. Plan Quality

Answer: C

NEW QUESTION 19

Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?

  • A. Estimate at completion
  • B. Cost performance
  • C. Schedule performance
  • D. To-complete performance

Answer: D

NEW QUESTION 20

In project management, a temporary project can be:

  • A. Completed without planning
  • B. A routine business process
  • C. Long in duration
  • D. Ongoing to produce goods

Answer: C

NEW QUESTION 21

Which Develop Schedule tool and technique produces a theoretical early start date and late start date?

  • A. Critical path method
  • B. Variance analysis
  • C. Schedule compression
  • D. Schedule comparison bar charts

Answer: A

NEW QUESTION 22
......