Q21. You are an application administrator. You received a change request to alter the relationship between an EPS node and its associated OBS element. 

What would be a prudent course of action to complete before moving forward with this change? 

A. Merge the old OBS element with the requested OBS element. 

B. Create a new OBS element per the change request. 

C. Determine which users would be affected. 

D. Delete the old OBS element per change request. 

Answer:

Q22. A Physical % complete activity has an original duration of 10, and a remaining duration of 10. The actual start is assigned to the activity. Physical % is updated to equal 80%. What is the remaining duration for this activity? 

A. 80 

B. 10 

C. 2 

D. 8 

Answer: D

Q23. You are an application administrator. You have been asked by your CEO to simplify the user interface for executives like her who are interested in high level summary information. Identify two ways to satisfy this request. 

A. Customize the toolbar in a saved view. 

B. Customize the EPS In a global view. 

C. Customize security In the OBS. 

D. Customize the Details fields in the Activity view. 

E. Customize the menu bars in a saved view. 

Answer: AE

Q24. You are in a governance organization that has established a project management methodology with work product and document requirements that must be included in every project. You want to create s global activity view that includes a filter to show only activities that have required work products and documents as per the methodology. Identify three actions that would help you to accomplish this. 

A. Create a Secure Global Activity Code. 

B. Create a Global Security Privilege for the Governance organization. 

C. Create a Global Governance Activity view. 

D. Group and sort by Governance deliverable. 

E. Create a filter available to the Governance organization. 

F. Create a custom portlet for a Governance dashboard. 

Answer: ACE 

Q25. Identify two business use case for templates. 

A. Document standard operating processes 

B. Customized projects for each user in each organization 

C. Facilitate scheduling standards for projects requiring audits 

D. Enhanced resource management and capacity planning 

E. Top-down budgeting and costed actuals 

Answer: AC 

Q26. Your customer wants to take advantage of capacity planning in portfolios. The customer would like to use generic resources, because they have greater flexibility to respond to changing costs by resource by location. In fact, they would prefer not to set up any roles at all in the database, because they perceive generic resources and roles to be duplicate effort. What would an appropriate response be to this customer? 

A. Use generic resources in Capacity Planning view, because they have greater ability to respond to changing costs. 

B. User generic resources for project financials, and mirrored roles for capacity planning. 

C. Use roles for planning and project financials to eliminate duplicate data maintenance. 

D. Integrate with HR systems to obtain automated generic resource pricing updates. 

Answer: B

Q27. You are a P6 administrator. You have received a change request against a configured global dashboard, involving the addition of a portlet. 

How would you make this change? 

A. Customize the user interface view 

B. Customize the Portfolio view 

C. Customize the dashboard 

D. Customize the layout 

Answer:

Q28. You are a project manager managing a large construction project. One of the pieces of heavy equipment required to dig the Foundation will most likely not be available until a specific date, because that equipment has been allocated to another, higher priority project. In that related project schedule you clearly see that in all likelihood, the activity in that plan that uses that equipment will also slip. You want to reflect this in your project schedule using a constraint. 

What would be the most appropriate constraint to use? 

A. Start On 

B. Start On or Before 

C. Start On or After 

D. Mandatory start 

Answer: C

Q29. You are a portfolio manager looking for a new portfolio that you manually created for your own use. You have clicked the Group By drop-down list in Portfolios. 

What option would you select to quickly find your portfolio? 

A. Global Portfolio 

B. Global filtered Portfolio 

C. User Portfolio 

D. User Filtered Portfolio 

Answer:

Q30. You are a portfolio manager. You opened a portfolio and you refreshed the filter. However, some of the projects that were previously in the portfolio are no longer there. 

What happened? 

A. You no longer have sufficient project-level security to view the "missing" project's data. 

B. Your web interface license was revoked to allow other users to interface with the projects. 

C. The value of the code assigned to the missing projects has changed. 

D. The projects were deleted when the filter was refreshed. 

Answer: A