Q1. You are a project manager on a fixed-bid contract. This contract has actually been positioned as a "loss leader" within your company because it is your first contract with this customer. The hope is that you can prove yourself to the customer and win additional business at higher margins down the road. The margins for this contract are very slim. 

What would be the best solution to set up in P6 to give you the visibility that you need to minimize the probable financial loss? 

A. Set a Mandatory Finish constraint at each contractual milestone and track schedule performance against the constraint. 

B. Set all activities in your project plan to Physical % Complete, and use Remaining Duration to track schedule performance. 

C. Set all activities in your project plan to Units % Complete, and use Remaining units to track schedule performance 

D. Set a Must finish By date at the project level, and track schedule performance using float in the project plan. 

Answer: B

Q2. Select the true statement regarding currencies. 

A. Only one base currency is supported per database. 

B. Currencies are updated daily per exchange rates. C. Only 10 currencies are supported in Primavera. 

D. Only two currencies are supported in Primavera. 

Answer: A

Q3. Identify two benefits of customizing user-interface views. 

A. Limit user access to functionality 

B. Lock down security privileges 

C. Administer users in the web interface 

D. Target application functionality 

E. User-based configuration 

Answer: AE

Q4. Your customer's project teams are cross-functional and global. Therefore, any standard reports must be generated at a standing day/time so that all affected resources and users have clearly defined timelines for data quality checks prior to report creation. Identify the P6 R8 feature that will address this requirement. 

A. Email monthly report to distribution list 

B. Send reports directly to printers at all user locations 

C. Schedule report generation to minimize performance issues 

D. Post generated reports to content repository 

Answer:

Q5. You are a program manager for a group of 10+ projects. You actually have a dedicated node for each program, and your owned projects reside under each node. Each program has its own unique requirements for viewing activity data. 

You do not want to ask for activity codes that would be visible to the entire organization. Which activity coding solution would serve the needs of the project managers in your programs? 

A. Create global activity codes. 

B. Create user activity codes. 

C. Create project activity codes. 

D. Create EPS activity codes. 

Answer:

Q6. Select two true statements about the Portfolio Analysis tab in Primavera P6 EPPM. 

A. Conducts a side-by-side comparison of an unlimited number of portfolios 

B. Conducts a side-by-side comparison of two projects 

C. Conducts a side-by-side comparison of two portfolios 

D. Conducts a side by-side comparison of one project displayed in different views 

E. Conducts a side by-side comparison of the same portfolio displayed in different views 

Answer: CE

Q7. Select two true statements regarding calendars. 

A. Global calendars are available to a subset of projects. 

B. Project calendars are available for the current project. 

C. Only a limited number of calendars can be created. 

D. Resource calendars are applied to all resources with the same primary role. 

E. Activity type determines whether the activity uses resource calendars when scheduling. 

F. Activity calendars are managed by individual users/resources. 

Answer: BE

Q8. Identify this icon: 

A. Customize Columns in the View 

B. Customize Tabs in the Details 

C. Customize GANTT Chart Options 

D. Customize and Save View 

Answer:

Q9. Identify this window. 

A. Portfolio 

B. Portfolio view 

C. Dashboard 

D. Project statistics 

Answer: B

Q10. Identify the true statement regarding administrative functions in P6 R8. 

A. Administrative functions can be performed in the client, or in the web interface. 

B. Administrative functions can only be performed in the client. 

C. Administrative functions can only be performed in the web interface. 

D. Administrative functions are determined at point of Installation. 

Answer: