NEW QUESTION 1

Which type of management focuses on ensuring that projects and programs are reviewed to prioritize resource allocation?

  • A. Project
  • B. Functional
  • C. Program
  • D. Portfolio

Answer: D

NEW QUESTION 2

Plan Risk Management is the process of defining how to:

  • A. Communicate identified risks to the project stakeholders.
  • B. Conduct risk management activities for a project.
  • C. Analyze the impact a specific risk may have on the project.
  • D. Address unexpected risks that may occur during a projec

Answer: B

NEW QUESTION 3

Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?

  • A. Identify Risks
  • B. Perform Qualitative Risk Analysis
  • C. Plan Risk Management
  • D. Perform Quantitative Risk Analysis

Answer: B

NEW QUESTION 4

Which tools or techniques are used during the Close Project or Phase process?

  • A. Reserve analysis and expert judgment
  • B. Facilitation techniques and meetings
  • C. Expert judgment and analytical techniques
  • D. Performance reviews and meetings

Answer: C

NEW QUESTION 5

In which type of organizational structure are staff members grouped by specialty?

  • A. Functional
  • B. Projectized
  • C. Matrix
  • D. Balanced

Answer: A

NEW QUESTION 6

Which Perform Quality Control tool graphically represents how various elements of a system interrelate?

  • A. Control chart
  • B. Flowchart
  • C. Run chart
  • D. Pareto chart

Answer: B

NEW QUESTION 7

Which is a tool or technique used in Define Scope?

  • A. Templates, forms, and standards
  • B. Change requests
  • C. Product analysis
  • D. Project assumptions

Answer: C

NEW QUESTION 8

Which Project Time Management process includes bottom-up estimating as a tool or technique?

  • A. Estimate Activity Resources
  • B. Sequence Activities
  • C. Estimate Activity Durations
  • D. Develop Schedule

Answer: A

NEW QUESTION 9

What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?

  • A. $50
  • B. $100
  • C. $125
  • D. $175

Answer: C

NEW QUESTION 10

In complex projects/ initiating processes should be completed:

  • A. Within a work package.
  • B. In each phase of the project.
  • C. To estimate schedule constraints.
  • D. To estimate resource allocation

Answer: B

NEW QUESTION 11

Which process determines the risks that might affect the project?

  • A. Perform Qualitative Risk Analysis
  • B. Identify Risks
  • C. Plan Risk Management
  • D. Perform Quantitative Risk Analysis

Answer: B

NEW QUESTION 12

Cost baseline is an output of which of the following processes?

  • A. Control Costs
  • B. Determine Budget
  • C. Estimate Costs
  • D. Estimate Activity Resources

Answer: B

NEW QUESTION 13

Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document?

  • A. Business case
  • B. Work breakdown structure
  • C. Requirements documentation
  • D. Risk register

Answer: C

NEW QUESTION 14

What is the primary benefit of meeting quality requirements?

  • A. Quality metrics
  • B. Less rework
  • C. Quality control measurements
  • D. Benchmarking

Answer: B

NEW QUESTION 15

The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?

  • A. Timing
  • B. Methodology
  • C. Risk categories
  • D. Budgeting

Answer: A

NEW QUESTION 16

Which is a communication method used in the Report Performance process?

  • A. Expert judgment
  • B. Project management methodology
  • C. Stakeholder analysis
  • D. Status review meetings

Answer: D

NEW QUESTION 17

Which project document is updated in the Control Stakeholder Engagement process?

  • A. Project reports
  • B. Issue log
  • C. Lessons learned documentation
  • D. Work performance information

Answer: B

NEW QUESTION 18

Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?

  • A. Sensitivity analysis
  • B. Three-point estimate
  • C. Modeling and simulation
  • D. Expected monetary value analysis

Answer: D

NEW QUESTION 19

Change requests are an output from which Project Integration Management process?

  • A. Direct and Manage Project Execution
  • B. Develop Project Management Plan
  • C. Close Project
  • D. Develop Project Charter

Answer: A

NEW QUESTION 20

Which Process Group and Knowledge Area include the Sequence Activities process?

  • A. Executing Process Group and Project Time Management
  • B. Executing Process Group and Project Cost Management
  • C. Planning Process Group and Project Time Management
  • D. Planning Process Group and Project Cost Management

Answer: C

NEW QUESTION 21

Job satisfaction, challenging work, and sufficient financial compensation are values related to which interpersonal skill?

  • A. Influencing
  • B. Motivation
  • C. Negotiation
  • D. Trust building

Answer: B

NEW QUESTION 22

Which type of agreement is legal, contractual, and between two or more entities to form a partnership, joint venture, or some other arrangement as defined by the parties?

  • A. Teaming
  • B. Collective bargaining
  • C. Sharing
  • D. Working

Answer: A